Gorakhpur’s Godhoiya nala revived under AMRUT 2.0

On 15 May 2026 the UP Chief Minister inspected the ₹495 crore Godhoiya nala project in Gorakhpur, built under AMRUT 2.0 by Jal Nigam (Urban). Physical progress was 95 per cent, with 9.25 km of drain, a 38 MLD sewage treatment plant and a 61 MLD pumping station built. He asked for completion by 15 June, before the monsoon.
- Date
- 15 May 2026, Gorakhpur
- Scheme
- AMRUT 2.0
- Cost
- ₹495 crore
- Agency
- Jal Nigam (Urban)
- Built
- 9.25 km drain; 38 MLD STP; 61 MLD pumping station; 14 bridges/culverts
- Benefit
- about 5 lakh people in the north of the city
The Godhoiya nala project in Gorakhpur: what happened?
Godhoiya was once a small river that turned into a dirty drain feeding Ramgarh Tal. It caused filth, mosquitoes and waterlogging. The project separates sewage from the channel so that only treated, clean water flows in it.
- The CM inspected the ₹495 crore Godhoiya nala project in Gorakhpur under AMRUT 2.0, due by 15 June. [UP CM press note]
- It has a 38 MLD STP; 9.25 km of drain has been built and physical progress is 95 per cent. [UP CM press note]
What does the project include?
- A pucca drain, diversion, interception and treatment of sewage.
- 17.50 km of the 17.94 km intercepting sewer line had been laid.
- The 38 MLD STP and the pumping station were on trial run.
- The RCC drain, about 9.5 km long and 9 metres wide, will carry rainwater via Ramgarh Tal and Tarkulani to the Rapti river.
- Separate underground sewer and drainage lines run on both sides; roads along the banks are being built.
What did the CM say?
- The project will end waterlogging in half the city before this monsoon.
- Plantation will be done on both banks during Van Mahotsav.
- Citizens should not throw plastic, cloth or waste into drains.
What can Prelims ask on the Godhoiya nala project in Gorakhpur?
- Godhoiya nala project, Gorakhpur: AMRUT 2.0; ₹495 crore; 38 MLD STP.
- Water flows via Ramgarh Tal and Tarkulani to the Rapti.
Read all of May 2026 in the monthly UP current affairs compilation →
How to use this in Mains
- Turning a dead drain into a treated channel solves both flooding and pollution.
Quotable data pointThe CM inspected the ₹495 crore Godhoiya nala project in Gorakhpur under AMRUT 2.0, due by 15 June [UP CM press note].
UP Information Dept, CM press note 2026-05-15: मुख्यमंत्री ने गोरखपुर में अमृत 2.0 कार्यक्रम के तहत 495 करोड़ रु0 की लागत से निर्माणाधीन गोड़धोइया नाला परियोजना के कार्यों का निरीक्षण किया (Hindi PDF)
Exam angle
GS-VI: urban water management in UP. Use Godhoiya as a model of reviving a dead drain by separating sewage and treating it.
Practice MCQs
Original practice questions (not PYQs).
The Godhoiya nala project in Gorakhpur is being built under
Answer (b) & explanation
UP CM press note, 15 May 2026.
Questions students ask about this
What is the Godhoiya nala project?
A ₹495 crore AMRUT 2.0 project in Gorakhpur to build a pucca drain and divert, intercept and treat sewage, reviving a dead drain.
What is the capacity of its STP?
38 MLD, with a 61 MLD pumping station.
Into which river will the drain carry rainwater?
The Rapti, via Ramgarh Tal and Tarkulani.