Ken–Betwa Link Project FAQs: water for Bundelkhand
Next story · 21 AugBRICS tourism ministers adopt Jaipur Declaration
A PIB Backgrounder of 21 August 2026 answers questions on the Ken-Betwa Link Project, the first river-interlinking project under the National Perspective Plan to reach implementation. Costing ₹44,605 crore, it moves Ken water to the Betwa basin through the 96.7 m Daudhan Dam and a 216.465 km canal. It will irrigate 10.62 lakh hectares in Bundelkhand by 2030.
- Cost
- ₹44,605 crore
- Dam
- Daudhan Dam, 96.7 m high, on the Ken (Panna and Chhatarpur, MP)
- Canal
- 216.465 km, Daudhan to Barua Sagar near Jhansi
- Irrigation
- 10.62 lakh ha
- Drinking water
- about 62 lakh people
- Power
- 103 MW hydro and 27 MW solar; completion 2030
The Ken-Betwa Link Project: what happened?
Bundelkhand, split between Madhya Pradesh and Uttar Pradesh, lives with drought. Rain is uncertain, groundwater is falling and farms fail. The Ken-Betwa Link moves water from the Ken basin to the water-short Betwa basin. It is India’s first river-linking project to reach the ground, so it is both a hope and a test.
- PIB published an FAQ backgrounder covering the scheme, benefits, land, rehabilitation and environment.
- The PM laid the foundation stone on 25 December 2024; the dam is under construction, the canal is yet to begin.
- The Lower Orr Project, Kotha Barrage and Bina Complex Multipurpose Project are under construction.
- Across the project, awards of about ₹629.87 crore were passed for 5,039 affected families, and about 96% has been paid.
Which areas benefit?
- MP: Chhatarpur, Niwari, Tikamgarh, Panna, Sagar, Damoh, Datia, Vidisha, Shivpuri and Raisen.
- UP: Banda, Mahoba, Jhansi and Lalitpur.
- The FAQ says it would not be right to claim the project will end drought; it improves water security and drought resilience.
What do affected families get?
- 22 villages are affected in MP: 8 in Panna and 14 in Chhatarpur.
- Land is acquired under the LARR Act 2013; families choose normal compensation or MP’s Special Package (approved 13 September 2023).
- Land compensation: the Act rate or ₹12.50 lakh per hectare, whichever is higher.
- Plot grant of ₹7 lakh in rural areas (₹6.50 lakh urban), or a lump sum of ₹12.50 lakh; extra help for eligible SC and ST families in Scheduled Areas.
What about Panna Tiger Reserve?
- Clearances: Wildlife (2016), Environmental (2017), Tribal Affairs (2017) and Forest (2023).
- Forest loss in the core of Panna Tiger Reserve is offset by compensatory afforestation, habitat management and catchment treatment.
- The Wildlife Institute of India prepared an integrated management plan (ILMP) for the Greater Panna area, for tiger, vulture and gharial.
- A council chaired by the MP Chief Secretary oversees it.
Which constitutional provisions govern river linking?
- List I (Union List), Entry 56: regulation and development of inter-State rivers and river valleys to the extent declared by Parliament by law to be expedient in the public interest.
- List II (State List), Entry 17: water, that is to say, water supplies, irrigation and canals, drainage and embankments, water storage and water power, subject to Entry 56 of List I.
- Article 262: Parliament may by law provide for adjudication of disputes on waters of inter-State rivers or river valleys.
What do the numbers show?
| Item | Figure |
|---|---|
| Total cost | ₹44,605 crore |
| Daudhan Dam height | 96.7 m |
| Link canal | 216.465 km |
| Irrigation | 10.62 lakh ha |
| Drinking water | about 62 lakh people |
| Power | 103 MW hydro + 27 MW solar |
| Affected families (project-wide) | 5,039 |
| Compensation paid | about 96% of ₹629.87 crore awarded |
How will Ken water reach the Betwa?
- Daudhan Dam stores water on the Ken in Panna-Chhatarpur
- Link canal (216.465 km) carries it north
- Canal joins Barua Sagar near Jhansi in the Betwa basin
- Water feeds irrigation, tanks and drinking water schemes
- Downstream, a minimum environmental flow is kept all year
Why does the Ken-Betwa Link Project matter?
| Angle | What to note |
|---|---|
| Water security | Dependable irrigation and drinking water for Bundelkhand. |
| Federalism | A joint MP-UP project under Union coordination. |
| Energy | 103 MW hydro and 27 MW solar. |
| Environment | Tests whether a tiger reserve can be protected alongside a dam. |
| Social | Large-scale rehabilitation under the LARR Act 2013. |
What are the challenges in the Ken-Betwa Link Project?
- Part of Panna Tiger Reserve’s core forest is lost, needing long-term conservation work.
- 22 villages are affected in MP; rehabilitation must be fair and on time.
- The FAQ itself says the project will not completely end drought.
- Groundwater gains depend on local geology and sustainable use.
- The canal is yet to begin, while completion is set for 2030.
What should be done next on the Ken-Betwa Link Project?
- Finish compensation and rehabilitation in a transparent, time-bound way.
- Carry out the Panna conservation plan with the funds earmarked.
- Start canal work and finalise DPRs of state-specific projects.
- Pair surface water with groundwater management and micro-irrigation.
What can Prelims ask on the Ken-Betwa Link Project?
- Ken-Betwa Link: first priority project under the National Perspective Plan for Interlinking of Rivers to be implemented.
- Daudhan Dam on the Ken: Panna and Chhatarpur (MP), about 40 km from Khajuraho.
- Canal ends at Barua Sagar near Jhansi.
- UP districts benefiting: Banda, Mahoba, Jhansi, Lalitpur.
- Inter-State rivers: List I Entry 56; water: List II Entry 17.
How to write about the Ken-Betwa Link Project in Mains
Practice question (15 marks, 250 words): The Ken-Betwa Link Project promises water security for Bundelkhand but raises ecological and social concerns. Critically examine.
- Intro: first river-linking project under NPP; ₹44,605 crore.
- Benefits: 10.62 lakh ha, 62 lakh people, power.
- Concerns: Panna Tiger Reserve, displacement, drought claims.
- Safeguards: clearances, ILMP, LARR Act package.
- Conclusion: balance; List I Entry 56 and List II Entry 17.
What should UPPCS aspirants note?
- UP districts that benefit: Banda, Mahoba, Jhansi and Lalitpur. The link canal ends at Barua Sagar near Jhansi.
How to use this in Mains
- As per PIB (2026-08-21): PIB FAQs describe KBLP: transferring water from Ken to Betwa basin via the Daudhan Dam and a link canal for Bundelkhand in MP and UP.
- Water for Bundelkhand has to be weighed against the ecological cost.
Quotable data pointPIB FAQs describe KBLP: transferring water from Ken to Betwa basin via the Daudhan Dam and a link canal for Bundelkhand in MP and UP.
PIB: PIB Backgrounder: Ken–Betwa Link Project, 21 Aug 2026
Exam angle
Mains: River interlinking: benefits and risks.
Practice MCQs
Original practice questions (not PYQs).
The Daudhan Dam of the Ken-Betwa Link Project is being built on
Answer (b) & explanation
PIB Backgrounder, 21 Aug 2026.
Which of the following UP districts benefit from the Ken-Betwa Link Project?
1. Banda
2. Mahoba
3. Jhansi
4. Lalitpur
Select the correct answer.
Answer (d) & explanation
PIB Backgrounder, 21 Aug 2026.
"Regulation and development of inter-State rivers and river valleys" is in
Answer (a) & explanation
Constitution of India, List I, Entry 56.
Questions students ask about this
What is the Ken-Betwa Link Project?
A river-linking project that transfers water from the Ken basin to the Betwa basin through the Daudhan Dam and a 216.465 km canal, to serve Bundelkhand in MP and UP.
What does it cost?
₹44,605 crore.
What are its benefits?
Irrigation for 10.62 lakh hectares, drinking water for about 62 lakh people, 103 MW of hydropower and 27 MW of solar power.
When will it be completed?
It is scheduled for completion in 2030.