GS3 · Energy / North-East

Subansiri Lower: first unit of India’s largest hydro project starts

Battle IAS current affairs title card: Subansiri Lower: first unit of India's largest hydro project starts (GS3 · Energy / North-East, 23 December 2025)

What happened

  • Unit-2 (250 MW) of the 2,000 MW (8×250 MW) Subansiri Lower hydroelectric project began commercial operation on 23 December 2025 [PIB].
  • NHPC runs the project, which PIB calls the country’s largest hydropower project [PIB].

Background

  • Subansiri is a tributary of the Brahmaputra. The dam is at Gerukamukh on the Assam-Arunachal Pradesh border (Dhemaji and Kamle districts) [NHPC].

Why it matters

  • Big dams in a seismic zone draw local protests. Mains answers should weigh clean power against downstream risk.

How to use this in Mains

GS-III Infrastructure: energy, ports, roads, airports, railways; investment models

  1. As per PIB (2025-12-23): unit-2 (250 MW) of the 2,000 MW (8x250 MW) Subansiri Lower hydroelectric project began commercial operation on 23 December 2025.
  2. Big dams in a seismic zone draw local protests. Mains answers should weigh clean power against downstream risk.
Quotable data point

Unit-2 (250 MW) of the 2,000 MW (8x250 MW) Subansiri Lower hydroelectric project began commercial operation on 23 December 2025.

PIB: MoP: Subansiri Lower unit commissioned, 23 Dec 2025

Exam angle

UPSC

Prelims: Subansiri, Brahmaputra tributaries.

Practice MCQs

Original practice questions (not PYQs).

Practice · UPSC

Installed capacity of Subansiri Lower

Answer (b) & explanation

PIB.

Practice · UPSC

Subansiri is a tributary of

Answer (b) & explanation

PIB.

Practice · UPSC

Operator

Answer (b) & explanation

PIB.

Go deeper

Official source: PIB: MoP: Subansiri Lower unit commissioned, 23 Dec 2025

facts from cited sources only; faculty review pending